Richardson, TX · Full investor rehab · 2025
Richardson investor rehab: $112.5K of work in 28 crew days
A rental investor client had a Richardson house with an oak kitchen, tile and carpet floors and baths that had not been updated in years. We scoped the whole house, ran every trade as one job and finished $112.5K of work in 28 crew days.
- total project
- $112.5K
- crew days
- 28
- kitchen, baths, floors, paint
- Whole house
Project total and crew days as published on our Google Business Profile (2025). Crew days are days our crews worked on site.
Before and after










What we started with
- Oak kitchen with old tile floors and appliances
- Carpet and tile in every room
- Original baths with dated vanities and tub surrounds
- Textured ceilings, old fixtures and window coverings
What we did
- Kitchen rebuilt: white shaker cabinets, quartz island and counters, stainless appliances
- LVP throughout, replacing carpet and tile
- Primary bath with a tiled tub surround under the windows, new vanity and black fixtures
- Secondary baths with new vanities, marble-look tops and tile
- Paint, lighting, ceiling fans, doors and hardware throughout
How we ran it
- A line-item scope the investor could take to their lender.
- Trades sequenced as one job, so there was no waiting between separate contractors.
- Daily photo updates, our own QC walk and a completion report at handback.
One team. Every trade. Documented completion.