Plano, TX · Full investor rehab · 2025
Plano investor rehab: a two-story house rebuilt from the studs out in 49 days
A two-story Plano house with dark wood paneling, a gutted kitchen, an outdated primary bath and a pergola that was rotting overhead. We ran it as one job with one project manager, from demo to final invoice in 49 days.
- total project
- $121.9K
- start to final invoice
- 49 days
- every room, plus the yard
- 2 stories
Project total and timeline as published on our Google Business Profile (2025).
Before and after








Before

After

What we started with
- Two-story living room in dark wood paneling, with a brick fireplace
- Kitchen opened up to the studs
- Wallpapered primary bath with an old tub and tile
- Worn stair treads and dated railings
- Pergola rafters rotted through
What we did
- Kitchen rebuilt with white shaker cabinets, a quartz island, a dark tile backsplash and stainless appliances
- Primary bath with a walk-in glass shower and a separate tub
- Wood paneling out, fireplace painted, walls and ceilings refinished
- LVP throughout, including the stair treads, plus painted railings
- Secondary baths with new vanities, tile surrounds and black fixtures
- Pergola rebuilt over the patio
How we ran it
- One project manager coordinated every trade, so the investor had one contact for the whole job.
- Line-item scope up front and written change orders for anything found behind the walls.
- Daily photo updates, our own QC walk and a documented closeout.
One team. Every trade. Documented completion.