How long does a make-ready turn take in DFW?
By Ashley Winton, Co-founder & CEO, Bridge & Build Renovations · Updated
- of our rental turns took one crew day
- 72%
- took two crew days or fewer
- 87%
- rental turns in the same window
- 90
Bridge & Build internal job data: 90 rental turns closed Jul 7 – Oct 5, 2026. Crew days are days a crew worked in the home, not calendar days. Not an industry or DFW average.
Crew days vs. calendar days
A crew day is a day our crew is working in the home. Calendar days run from award, or from move-out, to the day the home is ready for the next team. The gap between the two is where most turns lose time: waiting on a scope, an approval, a key, a part or the next trade.
Some of that gap is ours to control, like how fast we scope, staff and sequence the trades. Some sits with the owner or manager, like approvals and access. We report both numbers so nobody has to guess.
A real turn: Lewisville
Awarded on a Thursday, crew on site the same day. By Saturday, $6,700 of scoped work was complete. Our internal QC walk was Monday, and the home was ready for the client's cleaners after QC.
Three crew days. Five calendar days from award to cleaner-ready.
Why speed matters to the owner
A vacant home is not producing rent. At an example rent of $2,000 a month, one day is about $66 in potential gross rent. Faster production does not guarantee an earlier lease, but it removes one of the biggest delays between move-out and rent-ready.
What actually slows a turn down
- Trade scheduling: painters, flooring and plumbing booked separately, waiting on each other
- Materials: appliances, fixtures or flooring that have to be ordered
- An incomplete first scope, so new items show up mid-job
- Change-order approvals that sit in an inbox
- Access: no lockbox code, utilities off, HOA restrictions
- Failed QC and rework found at the owner walk
- Poor communication, so the next team does not know the home is ready
We manage these with a coordinated full bench of trades, daily photo updates on working days, our own QC walk and a documented completion report. It does not mean zero delays or zero punch items. It means fewer surprises and a clear handoff date.
How to get turns back faster
- Send access details and move-out photos with the work order, on move-out day if you can
- Agree on standard materials up front (paint colors, flooring, hardware) so they can be stocked
- Set an approval path for added scope, such as a pre-approved amount for small items
- Line up cleaners and leasing to start when the contractor's QC is done, not when the crew leaves
Common questions
How long does a heavy turn take?
It depends on the scope. Full paint, extensive flooring and kitchen or bath work add crew days and trade coordination, so a heavy turn gets its own production schedule with the line-item scope before work starts.
Do you count weekends?
Our turn numbers count crew days, the days a crew works in the home. The completion report shows the actual calendar dates. Weekend work depends on the schedule, access and the client's requirements.
How do I know the home is ready for cleaners?
After the crew finishes, we do our own QC walk and fix what we find. You then get a completion report with dates, photos and anything still open, so you can schedule cleaners and leasing with confidence.