How do you calculate holding costs on a DFW flip?

By Ashley Winton, Co-founder & CEO, Bridge & Build Renovations · Updated

holding cost per day on a $250K purchase
$82
if that rehab runs 30 days late
$2,466
typical construction time on our investor rehabs
4–8+ weeks

Example math at a 12% blended annual rate (purchase price × 12% ÷ 365), not a quote, a lender rate or a DFW average. Construction time is from our investor rehab history and depends on scope, permits, inspections and materials.

What counts as a holding cost

  • Loan interest on your purchase and rehab money: hard money, private money or a line of credit
  • Property taxes, which are a real line item in Texas even for a few months of ownership
  • Insurance, usually a vacant-property or builder's-risk policy
  • Utilities you keep on so crews can work and the house can be shown
  • HOA dues, lawn care and basic upkeep
  • The cost of your own cash sitting in this deal instead of the next one

You can total each line for your own deal. Most investors also want one number they can run in their head on a walk.

The quick formula: holding cost per day

The 12% is an example blended annual rate meant to cover interest, taxes, insurance and utilities together. Your real rate depends on your loan terms and the house, so use your own number if you know it. The point is a daily figure you can compare against a contractor's timeline.

Holding cost per day = purchase price × 12% ÷ 365

Example holding cost by purchase price and days late (12% ÷ 365)
Purchase pricePer day14 days late30 days late45 days late
$200,000$65.75$921$1,973$2,959
$250,000$82.19$1,151$2,466$3,699
$300,000$98.63$1,381$2,959$4,438

Read the middle row again: on a $250,000 purchase, a rehab that runs one month over costs about $2,466 of profit before a single change order.

Why the rehab timeline is the holding cost you control

You cannot change the tax rate, and your loan terms are set at closing. The big variable left is how many days the house sits between closing and listing, and most of those are rehab days. That is why the schedule deserves as much attention as the price when you compare contractors.

Five places flips lose days

  1. The scope takes too long. Every day you wait on a number is a day you cannot schedule crews or finish your lender package. Get a line-item scope before you close if you can.
  2. The scope misses the hard stuff. Paint and flooring are easy to price; structural, electrical and plumbing surprises are what stretch a schedule. Price the risky lines up front, even when the number is uncomfortable.
  3. Permits start late. When the work needs a permit, the clock starts when the application goes in, not when demo starts. Build permit review into the schedule from day one.
  4. Draws do not match the work. When the scope and the lender's draw schedule do not line up, the inspector cannot sign off and the money stops.
  5. Nobody owns the calendar. Separate trades with no single project manager means every handoff can slip a day.

How we keep your holding period short

We can walk the house and write a line-item scope before you close: free when you commit to us for the rehab, or $1,000 if you want it first, credited in full when you hire us. One project manager runs every trade, you get photo updates every working day, and our own QC walk happens before handoff.

We agree on a finish date up front. If we miss it, we pay the holding cost for each late day. The details are in your quote.

For reference, our Plano full rehab ran $121.9K and 49 days from start to final invoice, and our Richardson rehab ran $112.5K in 28 crew days (both 2025, from our published case studies).

Common questions

How do you calculate holding costs per day?

A quick rule of thumb is purchase price × an annual holding rate ÷ 365. At an example 12% rate, a $250,000 house costs about $82 a day. Use your real loan rate and expenses if you have them.

How much should I budget for holding costs?

Multiply your daily number by the full project length (closing, rehab, listing and the sale closing), then add a buffer for delays. The rehab is the part of that timeline you control most.

How can I reduce holding costs on a flip?

Shorten the days: get a line-item scope fast, price structural and permit work up front, match your scope to your lender's draw schedule, and use a contractor with one project manager and an agreed finish date.

Do contractors ever pay for delays?

Many do not. We agree on a finish date before work starts, and if we miss it, we pay the holding cost for each late day. The details are in your quote.

Is a holding cost the same as a vacancy cost?

Not quite. On a rental, the bigger number is usually the rent you are not collecting. On a flip there is no rent, so carrying costs are the main holding cost. Our guide on what a vacant day costs covers the rental side.

Got a flip under contract in DFW?

Send the address. We'll walk it, write a line-item scope and give you an estimated construction schedule you can run your holding-cost math against.

Call or text (682) 499-2969

Have photos? Text them to (682) 499-2969 for a price range.

Text usRequest walkthrough